瀝青混合料的攤鋪施工技術(shù)要求

來源:http://www.sybloom.com/ 日期:2023-11-13
1.待攤鋪機(jī)前的運(yùn)料車不少于5輛方可開始攤鋪混合料,避免停機(jī)待料,保持?jǐn)備佭B續(xù)。
1. There should be no less than 5 transport trucks in front of the paver before starting to pave the mixture, to avoid stopping and waiting for the material, and to maintain continuous paving.
2.當(dāng)有大功率攤鋪機(jī)時,可采用單機(jī)全斷面攤鋪,并通過試驗(yàn)段比較來確定采用單機(jī)還是雙機(jī)方案。不論采用何種攤鋪方案,都應(yīng)配備一臺可自動伸縮以調(diào)整寬度的攤鋪機(jī)。
When there is a high-power paver, a single machine full section paving can be used, and the single machine or dual machine scheme can be determined through comparison of experimental sections. Regardless of the paving scheme used, a paving machine that can automatically retract and adjust the width should be equipped.
3.當(dāng)采用3層瀝青結(jié)構(gòu)層時,攤鋪下層時不論是否分層施工,均應(yīng)采用掛線法施工,中、上層宜采用非接觸平衡梁或浮動基準(zhǔn)梁裝置施工,但在橋頭過渡段中層仍應(yīng)采用掛線法施工。
When using a 3-layer asphalt structure layer, the lower layer should be constructed using the hanging line method regardless of whether it is constructed in layers. The middle and upper layers should be constructed using non-contact balanced beams or floating reference beam devices, but the hanging line method should still be used for construction in the middle layer of the bridge head transition section.
4.當(dāng)采用雙機(jī)聯(lián)合攤鋪3層瀝青混合料結(jié)構(gòu)層時,下、中層兩幅搭接位置宜避開車道輪跡帶,前后兩臺攤鋪機(jī)軌道重疊30~60mm,中、上層搭接位置宜錯開200mm以上,兩臺攤鋪機(jī)前后的距離一般為10~20m以確?;旌狭喜话l(fā)生離析,且縱向接縫為熱接縫。表面層縱向接縫位置應(yīng)位于標(biāo)線處,其余各層應(yīng)分別緊挨路面標(biāo)線兩側(cè)。各層攤鋪后應(yīng)人工配合拍邊,使邊緣整齊、密實(shí)。
濟(jì)南瀝青混凝土
When using a dual machine joint paving of a 3-layer asphalt mixture structural layer, the overlapping positions of the lower and middle layers should avoid the lane wheel track. The tracks of the front and rear pavers should overlap by 30-60mm, and the overlapping positions of the middle and upper layers should be staggered by more than 200mm. The distance between the front and rear of the two pavers is generally 10-20m to ensure that the mixture does not segregate, and the longitudinal joint is a hot joint. The longitudinal joints of the surface layer should be located at the markings, and the remaining layers should be adjacent to both sides of the road markings. After each layer is paved, manual cooperation and edge tapping should be carried out to make the edges neat and dense.
5.攤鋪機(jī)開工前應(yīng)提前0.5~1h預(yù)熱熨平板不低于120℃。鋪筑過程中應(yīng)選擇熨平板的振搗或夯錘壓實(shí)裝置具有適宜的振動頻率和振幅,以提高路面的初始壓實(shí)度。熨平板加寬連接應(yīng)仔細(xì)調(diào)節(jié)至攤鋪的混合料沒有明顯的離析痕跡。
5. Before starting the paver, the preheating of the ironing plate should be 0.5 to 1 hour in advance, and the temperature should not be lower than 120 ℃. During the paving process, the vibrating or ramming device of the screed should be selected with appropriate vibration frequency and amplitude to improve the initial compaction of the road surface. The widening connection of the ironing plate should be carefully adjusted until there are no obvious signs of segregation in the paved mixture.
6.攤鋪機(jī)的螺旋布料器應(yīng)相應(yīng)于攤鋪速度調(diào)整到保持一個穩(wěn)定的速度均衡地轉(zhuǎn)動,兩側(cè)應(yīng)保持不少于送料器2/3高度的混合料,以減少在攤鋪過程中混合料的離析。
6. The spiral distributor of the paver should be adjusted to maintain a stable and balanced rotation speed corresponding to the paving speed, and the mixture should be kept at a height of no less than 2/3 of the feeder on both sides to reduce the segregation of the mixture during the paving process.
7.熱拌瀝青混合料的低攤鋪溫度根據(jù)鋪筑層厚度、氣溫、風(fēng)速及下臥層表面溫度按《公路瀝青路面施工技術(shù)規(guī)范》(JTGF40-2004)5.2.2條執(zhí)行,且不得低于規(guī)范表的要求。
7. The low paving temperature of hot mix asphalt mixture shall be in accordance with Article 5.2.2 of the Technical Specification for Construction of Highway Asphalt Pavements (JTGF40-2004) based on the thickness of the paving layer, temperature, wind speed, and surface temperature of the underlying layer, and shall not be lower than the requirements of the specification table.
8.瀝青混合料的攤鋪速度控制在2~6m/min為宜,上面層攤鋪速度不應(yīng)超過5m/min,其攤鋪用料量應(yīng)和拌合機(jī)的產(chǎn)量相適應(yīng)。
8. The paving speed of asphalt mixture should be controlled between 2-6m/min, and the paving speed of the upper layer should not exceed 5m/min. The amount of material used for paving should be suitable for the output of the mixer.
9.移動路脊法一般在上面層實(shí)施,具體施工方法如下:
9. The mobile ridge method is generally implemented on the upper layer, and the specific construction methods are as follows:
(1)采用移動路脊法施工的路段長度和路脊橫坡應(yīng)嚴(yán)格遵照設(shè)計實(shí)施。
(1) The length and cross slope of the road section constructed using the mobile ridge method should strictly follow the design implementation.
(2)根據(jù)采用移動路脊法的施工路段長度,在路段的起始端兩側(cè)取對角線,劃分兩個板塊施工,圖示如下:
(2) According to the length of the construction section using the moving ridge method, diagonal lines are taken on both sides of the starting end of the section, and construction is divided into two sections, as shown in the figure below:
(3)施工機(jī)械選擇及工藝
(3) Selection and process of construction machinery
應(yīng)采用可自動調(diào)節(jié)寬度的攤鋪機(jī)并輔以人工配合進(jìn)行攤鋪和修整。第一板塊施工時,攤鋪機(jī)根據(jù)路面寬度,采用不同寬度多幅攤鋪,每幅鋪筑均采用掛線法控制標(biāo)高,每幅按劃分的攤鋪寬度鋪至對角線時開始自動調(diào)縮攤鋪寬度,直至按攤鋪機(jī)小攤鋪寬度鋪完本幅,再另起一幅攤鋪,直至鋪完第一板塊,然后迅速以人工將對角線以外的多預(yù)料鏟除,并保證對角線順直。第二板塊也采用多幅鋪筑,攤鋪機(jī)不足部分由人工補(bǔ)齊。
A paver with automatic width adjustment and manual coordination should be used for paving and trimming. During the construction of the first section, the paver uses multiple pavers of different widths based on the width of the road surface. Each paver uses the hanging line method to control the elevation. When each paver is laid to the diagonal according to the divided paving width, the paving width automatically decreases until the small paving width of the paver is completed. Then, another paver is started until the first section is completed. Then, manually remove any unexpected areas outside the diagonal and ensure that the diagonal is straight. The second section also adopts multiple paving methods, and the insufficient parts of the paver are manually supplemented.
10.在路面狹窄部分、平曲線半徑過小的匝道、加寬部分、斜交橋頭等不能采用攤鋪機(jī)的部位可用人工攤鋪混合料。人工攤鋪應(yīng)嚴(yán)格控制操作時間、松鋪厚度、平整度等。
10. In areas where pavers cannot be used, such as narrow road surfaces, ramps with small flat curve radii, widened areas, and oblique bridge heads, manual paving of the mixture can be used. Manual paving should strictly control the operation time, loose paving thickness, flatness, etc.
11.嚴(yán)格按照設(shè)計銜接路面結(jié)構(gòu)層和橋隧過渡板(如下圖所示),并至少提前一天準(zhǔn)備好工作面,處理好欠壓實(shí)、松散、不平整等問題,并掃除松散材料和所有雜物。監(jiān)理工程師應(yīng)對此檢查驗(yàn)收。
11. Strictly follow the design to connect the pavement structure layer and bridge tunnel transition plate (as shown in the figure below), and prepare the working surface at least one day in advance to handle issues such as undercompaction, looseness, and unevenness, and remove loose materials and all debris. The supervising engineer shall inspect and accept this.
  • 上一條:濟(jì)南壓路機(jī)租賃:壓路機(jī)的分類
  • 下一條:濟(jì)南壓路機(jī)出租:壓路機(jī)有哪幾種?怎么分類?
  • 相關(guān)產(chǎn)品:

    国产亚洲日韩精品欧美一区二区| 国产精品35页| 欧美精品 日韩无码 国产| 91精品系列专区| 中文娱乐网久久精品一区二区| 蜜臀AV午夜精品久久| 欧美精品一级免费黄片| 三级麻豆精品在线观看| 久久精品少妇亚洲美女| 最新精品三级91在线播放| 9精品1国产一区| 热久久这里只有精品13| 精品中文三级亚洲| 国产日韩欧美精品一区不卡| 亚洲午夜精品久久久久久久久久久久 | 国产美日韩精品一区二区| 人妻性精品久久久| 国产精品-麻豆| 精品久久久久久久久久久换人妻| 欧美人妻日韩精品在线一区二区| 天堂在钱亚洲精品| 日后一区二区精品| 综合图区国产精品| www.四虎国产精品| 精品久久久黄色片| 国产精品高潮呻吟久久无码动态图| 美日韩精品淫片| 五月婷婷亚洲精品在线| 国产精品久久久影视视频网| 日日久夜精品91| 亚洲精品成人美女网站| 天天在线欧美精品免费看| 久久国产精品99国产精2021| 三级精品区| 色欲精品一区二区熟女| 欧美日韩成人精品不| 黑鬼乱交中文字幕亚洲精品| 精品偷拍74| 自拍无码精品一区二区三区| 久久九九欧美精品一区| 久久精品视频九九一区二区| 精品少妇人妻一区二区视频| 日韩欧美一区二区国产精品| 97精品久久久久久久久久精| 国产精品久久久久久久久久久不卡| 超久久精品| 大香蕉香蕉网成人精品视频 | 午夜精品影视国产一区在线麻豆| 成人精品久久久日韩| 精品日韩免费观| 国产精品婷婷一区二区| 一区久久精品| 國产精品無| 三级三级三级精品91区| 熟妇人妻精品一区二区视频小视频 | 在线 国产 精品 欧美| 国产精品久久久久久久av电影| 国产原创久久精品无码| 久久加勒比亚洲精品一区| 久久久久久国产精品操丝袜导航| 精品国产一二级在线| 久久精品黄色大全| 精品国产国产2021| 亚洲图日韩精品一区二区| 国产女同精品一级在线| 精品麻豆公司| 国产日韩欧美成人精品一区二区| 国产精品第一页高清网址| 女同精品裸精品裸精品一区二区三区| 97久久九九人妻精品二区| 黄色精品尺度| 亚洲精品日韩乱码人人爽人人澡人| 国产精品100夫妇激情啪发布| 99精品欧美一区二区三区综老∨| 美国,一区二区三区精品大黄片| 亚洲中文精品不卡| 黑人精品人妻| 97成人午夜精品| 久久亚洲精品黄色| 99国产精品免费观看视频re | 久久久精品极品一区二区2022| 日日噜噜噜噜夜夜爽亚洲精品| 精品国产电影在线观看 | 亚洲精品国产精品乱码在线观看 | 图产一区二区精品特级| 国产精品秘 麻豆电影| 免费成人电影日本精品| 最新69成人国产精品| 久久 国产精品| BBBAAA精品| 精品乱码吞精一区二区| 8X8Ⅹ精品一区二区三区| 久久久久99精品成| 久久精品亚洲精品日韩欧美| 色婷婷日韩国精品一区二区三区| 欧美日韩精品四区五区| 无码国产精品在线| 精品国产久久久免费视频 | 二o二四精品一区二区| 97精品人妻在线视频区| 韩国 日本 国产 欧美 精品| 国产先锋影音一区精品| 久久久精品高清一区二区| 亚洲精品1区二区| 91精品18一区| 偷拍日韩精品亚洲| 亚洲精品一区二区。| 国产精品视频美女啪啪| 国产精品潮吹呻吟久久AV| 日韩不卡一区精品| 国产精品第一区第一页| 久久久精品韩国电影| 黄色成人网站永久精品无码专区 | 少妇日本国产精品| 啪啪啪精品一区二区| 久久老司机精品久久| 久久精品无码一区二区麻豆蜜臀| 亚洲精品福利小视频| V区久久精品| 国产精品久久Av电影| 欧美囯产精品色幽幽| 国产精品成久久久久久三级四虎 | 欧美日韩激情精品国产成人| 人妻无码久久精品蜜臀AV| 国产精品在线欧美在线| 无码av福利亚洲精品| 精品一区二区三区四区麻豆| 精品国产电影九九九九| 91午夜精品久久| 95久久国产精品婷婷樱一区二区| 91页精品| 精品成人午夜91国产日韩精品| 欧美精品一区二区右手影院| 国产亚洲精品天堂| 亚洲老热精品久久久| 国产精品密臀久久| 精品国产片久久久久| 精品三级日本伦理片国产| 午夜精品视频电影网| 亚洲蜜臀久久精品| 热re99久久6国精品免费人妖| 99久久精品69| 久久人妻 精品二区| 欧美日韩 中文字幕 精品一区| 国产精品高清久久| 欧美日韩精品片| 亚洲国产精品原创| 亚洲精品中文久久久久| 国产精品少妇做爱一区二区不卡| 久久精品人妻免费人妻| 91粉嫩精品| 欧美精品黄频一区二区| 精品成人无码麻豆| 日本精品一本区久久久| 91精品不卡| 精品欧美二区三区久久久| 精品日本久久久久| 亚洲午夜精品福利电影| 国产91精品无码麻豆| 正在播放国产精品你懂的真多| 日韩国产123精品| 久久久亚洲精品高潮抽搐 | 久久精品三级国产麻豆电影网| 欧美精品久久久久电影| 欧美日韩综合精品日本无码| 国产精品美女高潮| 国际精品AV在线| 精品一区二区首页| 日韩国产综合在线精品一区| 国产基地精品| 免费看久久久久久国产精品试看 | 国产精品公司| 精品久久久久久久成人免费动漫| 中文娱乐网久久精品一区二区| 久久综合免费精品视频| 91在线精品秘| 69精品夜色国产| 天天干精品一区| 91精品国产粉嫩| 精品少妇久久高潮| 承认精品一区二区三区一级伊人久久久久 | 北条麻妃一区二区精品| 日韩高清精品一区| 综合色国产精品主播自拍欧美中文字幕| 欧美精品一区二区三区.COM| 亚洲精品欧美国产二区| 亚洲永久精品一| 国产精品美女内射| 九九热精品一区二区三区| 国产欧美精品二区二区| 国内精品人妻“| <